I knew the deadline was DECEMBER so I put a lot of effort into the post-production work at home, in my own time.
I set my own mini-deadlines which helped me to keep on track, although, I wasn't always focusing on one thing at a time. For example, whilst writing my script, I started drawing my storyboards. And, whilst I began my editing, I was also continuing my filming as I wasn't able to film as much as I wanted within the time I had. My ancilliary texts were also being researched and created in the free time that I had when I couldn't use the editing suites to edit my film.
Week Start: 25th October
COMPLETE SCRIPT
COMPLETE SCRIPT
Week Start: 1st November
COMPLETE STORYBOARDS
COMPLETE STORYBOARDS
Week Start: 8th November
COMPLETE ANIMATIC
Week Start: 15th November
FILMING
COMPLETE ANIMATIC
Week Start: 15th November
FILMING
Week Start: 22nd November
FILMING
FILMING
Week Start: 29th November
EDITING
Week Start: 6th December
EDITING
Week Start: 13th December
EDITING
Week Start: 6th December
EDITING
Week Start: 13th December
Evaluation
DEADLINE - THURS 16TH DECEMBER